Ok, just to add to the misery of the other MVV tram work, now they will be rebuilding the track on Orleansstr. The work will be done in two phases.
Tram #19 : (3.Apr - 17.Apr)
Tram is diverted over Grillparzerstr and wont be serving ostbahnhof
Tram #19 : (18.Apr - 31.May)
Tram will not be working between Karlsplatz Stachus and Max Weber Platz. There will be a #19 From Maxweberplatz to St. Veit Str, but over Grillparzerstr (not service ostbahnhof). Passing to Hauptbahnhof will be services by a replacement tram #39
Replacement Bus 119 (18.Apr - 31.May)
Will run between Maxweberplatz and Hauptbahnhof over Ostbahnhof
Bus #54 : (3.Apr - 31.May)
The Bus #54 will get split at Ostbahnhof into a 54N and 54S (north South). The 54S will run to a "normal" service from Ostbahnhof. The 54N will go out from its normal place at Ostbahnhof, but will return to FriedenStr (on the far side of ostbahnhof)
Bus #100 : (3.Apr - 31.May)
The Bus #100 will go out from its normal place at Ostbahnhof, but will return to FriedenStr (on the far side of Ostbahnhof)